Technical Specifications

Item Number

Description

Specification

1 Pumps

Wave powered high pressure pumps

2

Recovery

Pelton wheel (power/pressure recovery device – pumping)

3

Sensor systems

SCADA (Supervisory Control and Data Acquisition)

4

Controllers 

Integrated PLC (Programmable Logic Controller) for SCADA

5

Operating temperature

15-32 Celsius

6

Recovery rate

30%

7

Energy consumption (T-27 Celsius)

Self sufficient

8

Electrical supply

N/A – direct wave powered pumps

9

Power consumption

N/A – self sufficient

10

Power stability

N/A – wave energy regime variations mitigated with water storage supplementation

11

Production capacity

10,000 or 20,000 or other as required cubic meters per day

12

Production pressure

Residual pressure from brine stream enables the re-vpressurisation of the fresh water to be pumped to an altitude of up to 500m above sea level

13

Water storage

3-4 hours – allocate with on-shore or other (dependent on pipeline availability)

14

Water quality

WHO quality recommendations & South African regulations for potable water

15

Marine access

Up to 800 meters

16

Plant height above sea level

Up to 10 meters

17

Distance from shore

Wave powered high pressure pumps

18

Site on-shore allocation

5,000 square meters on land with a pipeline connecting the shore facility with a field of wave pumps

19

Site off-shore allocation/10m

Seabed: Field of wave pumps approximately 800m off-shore covering an area of approximately 5000m2 of seabed

Floating:Total surface area of sea that would be covered by floating devices would cover an area of 1000m2. Floatation devices are submersible and shall be slightly positively buoyant

20

Installation

Configuration: Containerised or skid mounted

21

Saline extraction

Up to 30,000 cubic meters per day with 1.5m sand around the intake head/discharge diffusers @ 20 to 27 Celsius

22

Extraction depth

10-15 meters

23

Marine pipe type

Shore dig and bury – entire pipeline route consists of 1m sand with no hard rocks

24

Tank size

Approximately 4,000 cubic meters

25

Main building

100 to 120 square meters with Operations Center, Data Center and office space

26

SWRO housing

Core systems for site security and communication

27

Core management systems

Wave powered high pressure pumps

28

Operator control systems

Operations and performance management systems

29

Marine monitoring

Surveillance of marine installations

30

Monitoring & management

Site and support systems for SCADA

31

Data management & integrated site data

Plant Performance and Efficiency Data production

32

Site development

Concrete slabs and paving

33

Plant type

SWRO system (Sea Water Reverse Osmosis)

34

Off-shore unit capacity

500kLD of fresh water per day

35

Off-shore unit sea state data

Production possible from moderate conditions of 1,4m wave height and an 18 second wave period

Marine Requirement Specifications

The site and other implementation pre-requisites for implementation ensure modular and fast deployment. Reasonable industry assumptions are made and changes required may result in scope variations. Meeting site criteria is essential for site selection for both plant and marine sections. The specification supports an off-shore pump system intake with physical water characteristics of TDS<36,000 ppm:

Feed Water Parameters

Units

Normal

Maximum

Turbidity NTU <10 <25
TSS mg/L <20 <50
TOC mg/L <5 <15
COD mg/L <15 <30
Total oil & grease mg/L Negligible <1
Total iron mg/L <0.2
Total manganese mg/L <0.05
Total colour Pt-Co/L <0.1 <20
Total hardness as CaCO3 mg/L <2,000 <3,000

Product Water Parameters

Units

Expected Value

Turbidity MTU <0.2
SDI <3

Additional Specifications

Contribution pipes with main dual intake pipes of up to 800m terminated with a manifold connecting the pipeline to a field of wave pumps and equipped with pre-filtration systems:

    1. Buried through the surf zone
    2. Anchored to the sea floor to a seawater depth of approximately 10~15m
    3. Each wave pump draws its water through a pre-filtration system buried up to 6m deep in sand

Discharge:

    1. Single brine discharge pipeline of up to 500m
    2. Buried through the surf zone and anchored to the sea floor
  • Brine dispersion diffusing is to be mounted at the correct distance from shore and the intake heads
  • No further treatment

Any work on the marine sector such as shore digging assumes sand and the ability to bury the entire pipeline route. Soil type of 1m sand along the marine routes required. Any rocks or cliffs in or out of the water that prevent the gravitational discharge feed of sea water result in a variation (change) request. Such tunneling, as well as under large roads, rail roads, etc. can result in scope variations.

      SWRO General Requirements

      1. The land with suitable soil and geotechnical conditions for executing the project, shall be provided to the Service Provider free of charge, for the entire duration of the project.
      2. Marine access and sufficient area for wave pump systems and pipelines. This includes the requisite areas on the seabed as well as floating components.
      3. The Customer is responsible of all community relationships and other social impact.
      4. The Service Provider is to be provided with permits for buildings, plans, regulatory and other zoning requirements as well as licenses within 21 days to enable the commencement of the installation of the System and its components.
      5.  Right of way for the related pipelines (off-shore marine section, between the intake pumps to plant, between plant and client reservoir (if applicable)) including installation thereof, shall be granted free of any charge, for the entire duration of the project.
      6. Access roads to site and along the pipelines shall be made available, free of any charge, for the entire duration of the project.
      7. The output of the system will vary as the sea/wave conditions vary. No penalties can be levied against the Service Provider for delivery that is comparable to the expected output during any particular sea state. The capacity of the storage needs to be large enough to modulate the differences between the actual output and the demands at any particular time.
      8. All approvals necessary for the execution of the project, including without limitation, with regards to permits, licenses, infrastructure and so on, whether to be granted by the client, or any governmental, municipal, private or other authority, shall be granted in a timely manner and in accordance with the project schedule. The party whose responsibility it is to procure these permits, license approvals and the like shall at all times keep the other party informed of any possible delays that may be experienced in obtaining these approvals.

      Our founding principle

      “Liberty is the right to have basic services, freedom is to have access to such services.”